超超临界机组蒸汽氧化及固体颗粒侵蚀的综合防治

摘 要:论述了超超临界机组所面临的突出问题--管道的蒸汽侧氧化及汽轮机叶片的固体颗粒侵蚀(SPE)的产生及对机组的危害,阐述了对SPE进行全方位全过程综合防治的思路:通过锅炉的合理选材,选择塔式炉,配置大容量旁路,采用无调节级汽轮机及合理的进汽结构,对汽轮机叶片作抗冲蚀处理,大幅降低热控保护的误动概率及锅炉强停次数,选择合理的启动和运行方式,慎用减温喷水等,能显著降低锅炉蒸汽侧氧化及氧化皮脱落造成的危害,极大地缓解汽轮机的固体颗粒侵蚀问题.
关键词:超超临界机组;蒸汽氧化;固体颗粒侵蚀;塔式锅炉
分类号:TK263.3;TM621.8  文献标识码:A
文章编号:1004-9649(2007)01-0069-05

Comprehensive prevention of steam oxidation and solid particle erosion for the ultra-supercritical unit

FENG Wei-zhong 

作者简介:冯伟忠(1954-),男,上海人,高级工程师,副总经理,从事电厂基建工程及生产技术管理工作.E-mail:002@wgq3.com
作者单位:冯伟忠(上海外高桥第三发电有限责任公司,上海,200137) 

参考文献:

[1]史进渊,杨宇,邓志成,等.超超临界汽轮机固体颗粒侵蚀的研究[J].动力工程,2003(4):2487-2489,2597.SHI Jin-yuan,YANG Yu,DENG Zhi-cheng,et al.Research on solid particle erosion of ultra-supercritical steam turbines[J].Journal of Power Engineering,2003 (4):2487-2489,2597.
[2]冯伟忠.900 MW超临界塔式锅炉技术特点及分析[J].动力工程,2006,26(1):15-21.FENG Wei-zhong.A 900 MW supercritical tower boiler's technical characteristics[J].Journal of Power Engineering,2006,26 (1):15-21.
[3]刘志江,李续军,刘向民.超临界压力汽轮机固体颗粒侵蚀的表面硬化处理技术[J].中国电力,2004,37(2):25-28.LIU Zhi-jiang,LI Xu-jun,LIU Xiang-min.Surface hardening treatment technology against solid particle erosion of supercritical pressure turbine[J].Electric Power,2004,37 (2):25-28.
[4]冯伟忠.900 MW超临界汽轮机的性能特点及分析[J].热力透平,2005,34(4):197-202.FENG Wei-zhong.Performance feature and analysis of 900 MW supercritical turbine[J].Thermal turbine,2005,34 (4):197-202.
[5]王乃宁,张志刚.汽轮机热力设计[M].北京:水利电力出版社,1987.WANG Nai-ning,ZHANG Zhi-gang.Thermal design of steam turbine[M].Beijing:Water Conservancy and Electric Power Press,1987.
[6]冯伟忠.1 000 MW级火电机组旁路系统作用及配置[J].中国电力,2005,38(8):53-56.FENG Wei-zhong.Functions and configuration of the bypass system for 1 000 MW class coal-fired power generation units[J].Electric Power,2005,38 (8):53-56.
[7]冯伟忠.900 MW超临界机组FCB试验[J].中国电力,2005,38(2):74-77.FENG Wei-zhong.FCB test for 900 MW supercritical units[J].Electric Power,2005,38(2):74-77.
[8]冯伟忠.外高桥二期2×900 MW工程调试特点[J].中国电力,2005,38(S0):55-59.FENG Wei-zhong.The commissioning features of 2×900 MW power generation units for Waigaoqiao Phase 2 Project[J].Electric Power,2005,38 (S0):55-59.

工成网